Blog/Hydraulic schematic: the 10 standard configurations
Contractors

July 12, 2026

5 min read

Updated August 6, 2026

Hydraulic schematic of principle: 10 standard configurations

A hydraulic schematic reads in three layers: the generator, the decoupling device, the secondary circuits. Ten configurations cover most domestic retrofit work, from a direct connection to a multi-fuel setup on a buffer tank. This article gives the selection table, the flow calculation per branch and the hot water temperatures the schematic has to hold.

Contents

A hydraulic schematic of principle reads in three layers: the generator, the decoupling device, the secondary circuits. What changes from one configuration to the next is the middle layer, and it is the one that decides everything else. The flow of each branch then follows from output and the chosen ΔT, with Q (m³/h) = P (kW) / (1.163 × ΔT), so 1.72 m³/h for a 10 kW heat pump at ΔT 5 K. On the hot water side, article 36 of the French arrêté of 23 June 1978, as amended in 2005, requires at least 50°C at every point of a distribution network holding more than 3 litres, and at least 55°C at the outlet of storage of 400 litres or more: those figures set where the cylinder, the recirculation loop and the blending valve sit on the schematic.

Reading a hydraulic schematic of principle

The symbols and connections to identify first

On a hydraulic schematic, start by identifying the flow and the return, with the arrows giving the direction of circulation. A tapping marks a branch to an emitter or a loop. A bypass is an alternative path, used to guarantee a minimum flow rate or to isolate a device without shutting the system down.

The components that structure the reading

The circulator carries the flow: its position relative to the generator and the decoupling device conditions everything else. Valves isolate, adjust or balance. The check valve prevents backflow when a circuit stops. The air vent releases air, the relief valve protects against overpressure. Identify these components and their direction before touching any setting.

What a schematic of principle does not tell you

A schematic of principle gives the topology, not the diameters or the pressure losses. On site, confirm the diameters actually installed, recalculate the pressure loss of the least favoured circuit and compare it with the available head. A check valve fitted backwards is enough to produce noise, a flow fault and a heat pump in safety mode.

The 10 standard configurations and their key device

The selection table

Each configuration comes down to one central device. These are the ten arrangements that cover most domestic retrofit work.

Configuration Key device on the schematic When to use it
1. Heat pump direct to radiators No decoupling Oversized emitters, sufficient water volume
2. Heat pump direct to underfloor heating Manifold with flow meters Loops of similar length, weather compensation
3. Two circuits at different temperatures Mixing 3-way valve Radiators and underfloor on one generator
4. Heat pump + buffer tank in series Buffer tank Short cycling, insufficient water volume
5. Heat pump + low-loss header Low-loss header Several circulators, mismatched flow rates
6. Heat pump + coil DHW cylinder 3-way DHW priority valve Combined heating and hot water production
7. Condensing boiler direct Unmixed low return Existing two-pipe network with a wide ΔT
8. Heat pump + boiler in backup Generator interlock Bivalent point, existing boiler retained
9. Heat pump + wood boiler stove Multi-source buffer tank Wood source with non-modulating output
10. Balanced DHW recirculation loop Loop balancing valve Long distribution runs, wait at the tap

Decoupling: low-loss header or buffer tank

The low-loss header separates primary and secondary flow rates without adding usable volume. The buffer tank adds volume and lengthens cycles. Choosing one for the other is the most common schematic error: a header does not cure short cycling, and a badly tapped buffer decouples nothing.

DHW priority and the temperatures to hold

DHW priority through a 3-way valve diverts the whole flow to the cylinder during a charge, which assumes the heating can wait. The schematic has to show the blending valve at the outlet and, on a recirculated network, the loop balancing valve. The anti-legionella cycle is driven from the controls, not from a permanently high setpoint.

The hot water temperatures that constrain the schematic

What the amended arrêté of 23 June 1978 sets

Article 36 sets thresholds that directly determine where components sit on the schematic. They apply to dwellings, workplaces and buildings open to the public.

Point of the network Requirement
Distribution network holding more than 3 litres At least 50°C at every point, excluding final draw-off pipes
Outlet of storage of 400 litres or more At least 55°C permanently, or a daily rise as set out in annexe 1
Draw-off points in rooms used for washing 50°C maximum
Draw-off points in other rooms 60°C maximum

Annexe 1 of the arrêté of 30 November 2005 gives the accepted temperature and duration pairs for the daily rise: it has to be read in the text itself, since the duration varies with the temperature reached.

What those thresholds impose on the schematic

Two opposing requirements coexist: produce and store hot for the sanitary risk, distribute tempered for the scalding risk. The schematic reconciles them with a thermostatic blending valve at the outlet of production, not by lowering the storage setpoint. On a cylinder fed by a heat pump, that constraint also weighs on the choice of electric backup.

DHW recirculation: length, balancing and control

A recirculation loop cuts the wait at the tap but requires the temperature to hold at every point of the loop. Insulate, limit the loop to the sections that need it, fit balancing devices on each riser and interlock the pump. An unbalanced loop creates cold branches that become the sanitary weak point of the network.

Configurations with a heat pump and mixed generators

Heat pump direct: feasibility conditions

Connected directly to radiators or underfloor heating, feasibility rests on the flow temperature the emitters accept and on the available water volume. Check the manufacturer's minimum flow, the balancing of the network and the consistency of the ΔT. Key settings: weather compensation curve, an appropriate circulator speed, a magnetic filter protecting the heat exchanger.

Heat pump and boiler in backup: control logic

The heat pump covers the base load, the boiler takes over at the bivalent point defined at the sizing stage. On the hydraulic side, plan for check valves, a 3-way valve or decoupling through a tank depending on the flow rates involved. The control logic must interlock both generators to rule out double heating, and keep priority on the heat pump for as long as the outdoor temperature allows.

Heat pump and wood boiler stove: decoupling and wood safeties

With a non-modulating wood source, the circuits are separated by a buffer tank that absorbs the output peaks. The schematic has to show the thermal relief valve, the cooling loop and the overheat safety, all non-negotiable on a solid fuel appliance. Add a dirt separator and an air vent at the high point of the primary.

Commissioning and handover of the schematic

Labelling and refilling

Before restarting, label the flows, returns and adjustment devices, then vent methodically from the high point down to the generator. Check cold pressure and tightness before any rise in temperature. An air pocket at the high point skews the balance and makes the circulator work in cavitation.

Commissioning checks

Measure flow, return and ΔT on each circuit, compare with the design ΔT, then record the flow rates at the manifold. Set the circulators to a fixed speed or constant pressure depending on the network type. A correctly set schematic shows quickly: less noise, even temperatures, longer generator cycles.

The as-built schematic as a file document

The schematic of principle used at the design stage is not the deliverable. What you hand over is the as-built schematic, labelled, dated and signed, together with the sizing note, which Argile produces to EN 12831-1 from the survey readings, and the commissioning readings. It is the document that lets another installer take over the system without rediscovering it, and the one that protects you if the configuration is ever challenged.

Key figures

1.72 m³/h

Flow for 10 kW at ΔT 5 K

≥ 50°C

DHW at every point of the network

≥ 55°C

Outlet of storage of 400 L and over

Frequently asked questions

Flow follows from output and the chosen ΔT, with Q (m³/h) = P (kW) / (1.163 × ΔT). A 10 kW heat pump at ΔT 5 K calls for 1.72 m³/h; the same unit at ΔT 7 K calls for only 1.23 m³/h. Carry that flow onto every branch of the schematic, then check that the circulator covers the actual head of the least favoured circuit, fitting losses included.

Share this article

Pierre-Louis Guhur

Pierre-Louis is CEO and co-founder of Argile. He holds a PhD in machine learning, written at Inria, and renovated a house with his own hands in 2017 before founding the company. On the blog he writes about what he implements in the software: the 3CL-DPE 2021 method, NF EN 12831 and building physics as a calculation engine has to handle them, assumption by assumption.

Further reading

Heat pump sizing note

Calculated to NF EN 12831-1

General information

Beneficiary

Mrs Margaret Hughes

Email

contact@argile.ai

Phone

+44 7700 900457

Works address

7 Rosewood Close, Sheffield

Air-to-water heat pump

Model

Alféa Extensa S. 10

Make

Atlantic

Rated output

10 kW

ηs at 35 °C / 55 °C

195 % / 154 %

COP

3,5

Controller

Classe VI

EPREL no.

2491075

Heat loss of the home

6,0 kW

Output at the design temperature

5,80 kW

3,59 kW

7,78 kW

0 %

60 %

130 %

Coverage of the demand

Equipment output / heat loss of the home

97 %

Sizing of the appliance

Roofs

Transmittance W/m².K

1,8

Area

65,2

Heat loss W/K

135,0

Floors

Transmittance W/m².K

0,6

Area

63,0

Heat loss W/K

15,6

Thermal bridges

Conductivity W/K/m

0,4

Lengths m

33,4

Heat loss W/K

12,5

Façades

Transmittance W/m².K

0,9

Area

162,4

Heat loss W/K

151,4

Openings

Transmittance W/m².K

1,2

Area

5,5

Heat loss W/K

10,9

Air renewal

Air change rate h⁻¹

0,8

Heat loss W/K

102,3

Temperature difference

Outdoor design temperature

-7 °C

Heat pump cut-off temperature

5 °C

Indoor set temperature

19 °C

DeltaT

14,0 °C

Construction coefficient

Volume (area × ceiling height)

378,0 m³

Equivalent G value

1,13 W/m³/K

With argile

The compliant sizing report, generated automatically

Compliant with EN 12831-1 and built from the data collected during the site visit, the sizing report comes out of the flow with no extra work, ready for the customer's file.

ContractorsMay 20, 2026
Pressure loss in hydraulic heating networks

A network's pressure loss is the sum of the linear losses per section and the fitting losses, set against the head available at the circulator. The calculation belongs to the sizing stage, not to the day the network starts whistling. This article gives the section-by-section method, the flow-versus-diameter table and the orders of magnitude worth carrying on site.

5 min read

ContractorsJuly 24, 2026
Air leakage test: measuring airtightness

Air leakage testing is judged on an enforceable figure, not on a draught: 0.60 m³/(h·m²) of heat-loss envelope for a detached house, 1.00 for multi-unit housing, under article 19 of the French order of 4 August 2021. Two uplifts can move that target, sampling and works still to come after handover, and both are settled on site rather than in the report. Here are the thresholds, the corrections, and the report to demand from the tester.

5 min read

Reveal your expertise

One demo, and you see your expertise proven.

Contact us