Blog/Underfloor heating screed: dry, flowing or cement screed
Contractors

May 19, 2026

•

8 min read

•

Updated October 16, 2026

Screed over underfloor heating: dry, flowing or cement, the real framework

A screed over underfloor heating comes in three families: cement screed, flowing screed (calcium sulphate or cement) and dry screed with heat-spreader plates. Wet screeds cover the pipes by at least 30 mm for a flowing screed (CSTB, guide 3578_V4) and fall under traditional texts. Dry screed is covered by no traditional code and goes through the system's technical approval, which changes your insurance and your quotation. Here are the thicknesses, drying and heat-up times, the timber floor case and a typical cross-section layer by layer.

Contents

A screed over underfloor heating comes in three families: traditional cement screed, flowing screed (anhydrite or cement) and dry screed with heat-spreader plates. The first two embed the pipes and fall under traditional texts. The third does not. No traditional installation code covers dry screed over underfloor heating. The French screed code covers only screeds and slabs based on hydraulic binders, which rules out a gypsum-fibre or plasterboard panel by definition, and the French approvals committee maintains system families explicitly defined as falling outside the underfloor heating code. The applicable route is therefore the system's own technical approval, which places the works outside the traditional field. That is not an obstacle, it is a constraint on your documentation, your insurance and the wording of your quotation, and it is the first thing to settle before anyone starts comparing thicknesses.

Underfloor heating screed: the three families in one table

Criterion Cement screed Anhydrite flowing screed Dry board screed
Cover above the pipe At least 3.5 cm on SC1 insulation (AQC) 30 mm minimum, 8 cm maximum None, board thickness set by the system
Drying before the covering About 1 week per centimetre, then measure Down to 0.5% or 1% residual moisture None
Framework NF DTU 26.2 and NF DTU 65.14 Professional rules of July 2022 The system's technical approval

A wet screed embedding underfloor heating must be at least class C20-F4. Flowing screed wins on large areas: self-levelling, it surrounds the pipe with no voids. Cement screed keeps the small rooms, at the cost of a tight joint layout. Dry screed is the renovation choice: timber floor, occupied home, short deadline.

Anhydrite screed over underfloor heating: what it demands

Calcium sulphate tolerates 300 m² without a joint, but it brings three milestones: the first heat-up, from the 7th day after pouring and in 5°C steps; the carbide bomb residual moisture measurement; the surface preparation set by the product data sheet before bonding. It remains more sensitive to moisture than a cement binder.

The applicable framework: what exists and what does not

Why the screed code cannot apply

The French screed code NF DTU 26.2, April 2008 edition amended in May 2015, is titled "Screeds and slabs based on hydraulic binders". Its scope is in its title. A gypsum-fibre board or a timber panel is not a hydraulic binder, so the text does not cover it. Its residual role on an underfloor heating job is real but narrow: its annex A defines the method for measuring substrate cohesion before the covering goes down, a method the CSTB refers to explicitly.

The technical approval route, and what it implies

Even flowing screeds, hydraulic binders though they are, spent twenty years under technical approval for want of a traditional text, until the French approvals committee moved part of the family into the traditional field in 2019 and the UNECP-FFB and CAPEB professional rules of July 2022 took over. Dry screed has had no such transition. In practice you need a system holding a valid technical approval, installation strictly within its stated scope of use, and notice to your latent defects insurer before the job starts.

The framework, system by system

Solution Reference text Scope
Traditional screed or slab on a hydraulic binder NF DTU 26.2 Traditional field
Cement or calcium sulphate flowing screed UNECP-FFB and CAPEB professional rules, July 2022 Traditional field since the approvals committee transition
Water-based heated or reversible floor NF DTU 65.14, July 2023 edition Traditional field, with exclusions per part
Low-temperature reversible water floor CSTB technical guide 3164 Technical prescriptions guide
Dry screed over underfloor heating The system's own technical approval Outside the traditional field

The practical consequence fits in one line: your reference figures are not general, they are those of the system installed, and that document belongs in the site file.

Screed thickness over underfloor heating: the written values

Thickness is counted above the pipe, not from the insulation. The floor falls under NF DTU 65.14; the figures for cover are published by the CSTB and adopted by the 2022 professional rules.

Configuration Cover above the pipe Source
Type A floor and reversible floor 30 mm minimum at every point CSTB, guide 3578_V4, table 5
Castellated insulation panel 25 mm minimum above the boss CSTB, guide 3578_V4, table 5
Type C floor 20 mm minimum at every point CSTB, guide 3578_V4, table 5
All flowing screed configurations 8 cm maximum at every point CSTB, guide 3578_V4, table 5
Typical cross-section of a hot-water floor At least 3.5 cm on SC1 insulation, 4 cm on SC2a AQC, pathology sheet E.04
Dry screed Board thickness of the system The system's technical approval

Below the minimum, the screed cracks along the pipes: the AQC documents a defect on cover reduced to 15 mm. For the height to reserve, add insulation, cover, adhesive and covering: in the worked example of the same sheet, a mortar-bed installation on 5 cm of insulation needs 20.5 cm. That total decides the thresholds in renovation.

What a dry screed genuinely saves, with figures

Drying and the residual moisture measurement

That is the main gain and it is measurable. On a calcium sulphate flowing screed, laying the covering requires residual moisture down to 0.5% for PVC, rubber, linoleum, wood flooring, resin or a waterproofing system under tile, and 1% for tile or natural stone in E1 and E2 rooms. The measurement is taken with the carbide bomb method, with at least two samples per room under 100 m² then one per additional 100 m², under the responsibility of the contractor laying the covering (CSTB, guide 3578_V4).

Movement joints and the first heat-up

A wet screed requires a joint layout, and the gap between binders is enormous. Calcium sulphate, 300 m² without a joint with a maximum length of 25 m. Cement, 40 m² and 8 m as the general case. Add the first heat-up, possible from the 7th day on a calcium sulphate screed and carried out in 5°C steps, then heating switched off for at least 2 days before and 2 days after the covering is laid, grouting included. Those milestones are set out in our article on the site sequence for a heat pump on underfloor heating.

Drying time and gradual heat-up: the honest comparison

Milestone Cement screed Anhydrite flowing screed Dry screed
Drying time before the covering About 1 week per centimetre, then measure Weeks to months depending on thickness and conditions None
Carbide bomb residual moisture measurement Depending on covering and data sheet Mandatory, thresholds of 0.5% or 1% by covering Not applicable
Movement joint layout 40 m² and 8 m as the general case 300 m² and 25 m Per the system's technical approval
First heat-up Delay set by NF DTU 65.14 and the system data sheet From the 7th day after pouring, 5°C steps The system's own protocol
Heating off around laying 2 days before and 2 days after, grouting included 2 days before and 2 days after, grouting included The system's own protocol
Applicable framework Traditional text Traditional text Technical approval, outside the traditional field

The first heat-up tests the screed and the circuit, it does not force drying: record every step in the report. What a dry screed does not remove: the pipe layout drawing, the pressure test, the record keeping, and your liability for the thermal resistance of the build-up.

Thermal resistance, the real point to watch

What is capped and what is not

Configuration Quantity Published limit
Reversible floor Covering thermal resistance, including acoustic layers above the heating elements 0.09 m².K/W, CSTB technical guide 3164
Reversible floor Total thermal resistance above the pipe 0.13 m².K/W, CSTB technical guide 3164
Reversible floor Surface mass of the covering works above the insulation 160 kg/m², CSTB technical guide 3164
Heating-only floor Thermal resistance of the build-up No institutional figure published, see the system's technical approval

The 0.10 to 0.15 m².K/W figure found everywhere is not traceable to any verifiable institutional document. It may well be right, it is not enforceable, and it therefore has no business appearing on a quotation as a requirement.

The calculation is done layer by layer

Add up the resistance of every layer above the heating element: dry screed boards, any acoustic underlay, adhesive, covering. That total is what you compare against the limit in the system's approval. An acoustic underlay added late in the job to fix a noise complaint can on its own push the build-up outside the scope of use, and nobody notices before winter. On the concept itself, see what thermal resistance R actually covers.

What you write on the quotation

The exact reference of the system and its approval, the build-up layer by layer with its total resistance, the covering fixed, and a note that any change of covering or added underlay has to go back through that calculation. Three extra lines on a quotation that carries the equipment and works from the works plan, and a potential complaint becomes a variation order.

Lightweight screed on a timber floor: load first

On a timber floor, the question is what the joists can carry. Indicative loads (orders of magnitude from manufacturer data sheets), covering extra:

Layer above the timber floor Indicative load
Traditional cement screed, 5 cm About 100 kg/m²
Lightweight cement screed, 5 cm 45 to 60 kg/m²
Dry board system 15 to 25 kg/m²

They add to the imposed load of a dwelling, 1.5 kN/m² (about 150 kg/m²). Record span, section, spacing and condition of the joists before pricing, and have a structural engineer settle any doubt. Dry screed is the lightest and brings no water into the timber, but it needs rigid decking: a floor that deflects cracks a tiled finish as surely as a screed that is too heavy. The calculation and substrate preparation are detailed in our article on lightweight screed over a timber floor, and complete dry systems in our article on dry underfloor heating in renovation.

Typical underfloor heating cross-section, layer by layer

From bottom to top, the order to describe on the quotation and to photograph on site:

Layer Wet screed, cement or flowing Dry screed
1. Substrate Slab or floor, flatness checked with a 2 m straightedge Same, rigid decking on a timber floor
2. Edge Compressible perimeter strip, 5 or 8 mm minimum Continuous resilient perimeter strip
3. Insulation SC1 or SC2a class panel, thermal resistance compliant with NF DTU 65.14 The system's grooved insulation panel
4. Emitter Pipes fixed to the insulation at the design spacing Pipes set in aluminium heat-spreader plates
5. Cover or boards C20-F4 screed minimum, 30 mm above the pipe in flowing screed One or two layers of staggered boards, bonded or screwed per the system
6. Covering Adhesive and tile, wood flooring or PVC, after moisture measurement Covering allowed by the technical approval

The thermal resistance to check is that of layers 5 and 6 and any underlay. Layer 3 holds the heat back from going down: do not confuse it with an insulating screed, which serves as a levelling layer, as our article on insulating screed thickness explains.

Installation: the points that produce claims

Substrate, flatness and load-bearing capacity

A dry screed does not correct an uneven substrate. Check with a 2 m straightedge, treat dips, remove hard high points, verify load-bearing capacity on a timber floor and the absence of deflection under load. On moisture, the substrate has to stay dry, otherwise the boards swell and go out of level. In renovation, those three checks are done before pricing, not after signing. Sizing the emitter itself, spacing included, is covered in our article on low-temperature underfloor heating.

Laying the pipework under the boards

Lay to the spacing set at the sizing stage, fix without crushing the insulation, leave unheated zones under fixed furniture and around planned penetrations. Carry out the pressure test before closing up and keep the network under pressure while the boards go down: it is the only moment when a crushed pipe can be repaired without dismantling. Photograph, number, date.

Edges, decoupling and joints

A continuous resilient perimeter strip with no contact against any hard point, systematic decoupling on timber or cracked substrates, movement joints at thresholds and continuity with the substrate's existing joints. In double-layer systems, stagger the boards and respect the fixing method the system specifies, bonding or screwing, never a mix decided on site. On the acoustic side, see acoustic insulation of intermediate floors, bearing in mind what any underlay does to thermal resistance.

Handover, insurance and the sales argument

The heat-up protocol

It comes from the system, not from a general rule, since no traditional code applies. Raise the temperature in steps, record flow and return temperatures and the pressure, come back down, and keep a report. Where the generator is a heat pump, connection and commissioning follow the same record-keeping logic as on a wet screed, and if the system also has to cool, the limits tighten considerably, as our article on underfloor cooling sets out.

What the insurer expects

A system holding a valid technical approval, installation within its stated scope of use, and prior notice to your latent defects insurer that a non-traditional technique is being used. The system's document goes in the file and its reference is quoted on the tender. Simple traceability kept as the job runs beats a reconstruction after a claim.

Justifying the price against a cheaper bid

Dry screed stands on measurable facts: less added load, no mixing water on site, no drying and no residual moisture measurement before the covering, hence a programme that holds in an occupied dwelling. It costs more in substrate preparation and in controlling thermal resistance. A competitor pricing the kit without pricing the levelling, the threshold rework and the verification of the build-up is not selling the same works, and that is exactly what can be demonstrated line by line. On what the final covering does to thermal behaviour, see the impact of the floor covering on thermal mass.

Key figures

30 mm

Minimum cover above the pipe, flowing screed

0.09 m².K/W

Max covering resistance, reversible

2 days

Heating off before and after laying

Frequently asked questions

A water-based heated floor falls under NF DTU 65.14 of July 2023, which covers floors in slabs and embedding layers with exclusions per part. A traditional cement screed falls under NF DTU 26.2 and a flowing screed under the UNECP-FFB and CAPEB professional rules of July 2022. Dry screed is covered by no traditional code: NF DTU 26.2 only covers hydraulic binders, which rules out a gypsum-fibre board. It goes through the system's technical approval, and that document is the reference.

Share this article

Louis Airy

Louis is COO of Argile. After four years in strategy consulting and close to two as chief of staff in home adaptation and reuse, he joined Argile in March 2024. In daily contact with certified renovation companies, he follows French energy saving certificates, renovation subsidies and reduced VAT, and revises the affected articles whenever a rate changes. What he writes is what he then checks against real quotes.

Further reading

Customers

/

Camille Martin

Details

Dwelling

Works plans

Quotes

Admin & finance

Quote no. D2026-0042

History

Analysis

Preview

Save

The property

Energy renovation

Information

4

The quote

5

Terms

Next step

The quote

No.

Description

Qty

Unit

Unit price excl.

Total excl.

VAT

Price incl.

1

Installing an air-to-water heat pump

Technical specifications of the heat pump (mandatory)

3 STILL TO FILL IN

Area heated by the heat pump (m²)

e.g. 120

Seasonal energy efficiency ηs (%)

e.g. 126

Controller class

I

II

III

IV

V

VI

VII

VIII

1.1

Installing an air-to-water heat pump

10 600,00 €

11 183,00 €

1.1.1

Air-to-water heat pump 14 kW

1,00

U

3600,00

3 600,00 €

5,5%

3798,00

B

I

U

Heat output +7 °C / +35 °C: 13.00 kW. Heat output -7 °C / +60 °C: 10.10 kW. Seasonal space heating efficiency (35 °C / 55 °C): 150 % / 117 %.

1.1.2

Heat pump fitting and commissioning

1,00

U

7000,00

7 000,00 €

5,5%

7385,00

Add a line

2

External wall insulation (EWI)

2.1

External wall insulation (EWI)

22 500,00 €

23 737,50 €

2.1.1

Polystyrene insulation, R of 3.7 m².K/W or above

120,00

M2

120,00

14 400,00 €

5,5%

15192,00

2.1.2

Insulation labour package

120,00

M2

75,00

9 000,00 €

5,5%

9495,00

Discount

-900,00 €

8 545,50 €

With argile

Flawless quotes, straight from the works plan

Equipment, labour and accessories come from the works plan, VAT applies line by line, grants are deducted from the amount due and the mandatory wording is already written: the quote goes out for signature without a proofread.

ContractorsSeptember 30, 2026
Underfloor Heating System Sludge Removal: Diagnosis and Treatment

In underfloor heating, you are dealing with trapped air when air comes out at the manifold and the flow rates recover; you are dealing with sludge when the flushing water turns blackish, with marked temperature differences between loops and flow meters that stay low even though the circulator is running properly. Treatment is carried out loop by loop at the manifold until you recover even return temperatures, then the system is refilled with filtration, a magnetic sludge separator and inhibitor to prevent recurrence within two seasons. To frame the work and the evidence you need to keep, rely on the current energy-savings certificate scheme dedicated to heating system sludge removal, which sets the eligibility conditions and the required traceability.

6 min read

ContractorsOctober 10, 2026
Heating wholesaler: how to choose, negotiate and price your purchases

To buy at the right price and secure lead times, start by opening a trade account with a credit line and payment terms, most often 30 days end of month, as set out in the wholesaler’s Terms & Conditions of Sale (CGV). On pricing, the only meaningful benchmark is the “net price” after discount, not the list price, as framed by Article L441-3 of the French Commercial Code on transparency of B2B selling terms. When you quote, think in terms of delivered-to-site purchase cost (product + freight + handling) and then apply a sales mark-up factor, not an intuitive margin, to absorb your overheads and availability risks.

6 min read

Reveal your expertise

One demo, and you see your expertise proven.

Contact us