The issue holding the job up: how much does a lightweight screed on a timber floor weigh?
With a lightweight screed on a timber floor, what matters is not the installation itself but the load you are transferring into the joist system. The calculation is straightforward. Area load = declared mortar density (kg/m³) multiplied by finished thickness (m).
2026 benchmarks: area load by binder, density and thickness (kg/m²)
| System | Density (kg/m³) | 40 mm (kg/m²) | 60 mm (kg/m²) |
|---|---|---|---|
| Cement + EPS beads | 500 | 20 | 30 |
| Cement + perlite | 800 | 32 | 48 |
| Cement + expanded clay aggregate | 1100 | 44 | 66 |
| “Lightweight” anhydrite | 1400 | 56 | 84 |
What you really add: mortar weight + residual water + flooring + lightweight partitions
Think in terms of cumulative loads, not just “screed weight”. Until the moisture content reaches the specified level before flooring, residual water still counts. And a partition wall is mainly a line load.
| Added item | Typical order of magnitude | Unit |
|---|---|---|
| Residual water (drying phase) | 5 to 15 | kg/m² |
| Tiles + adhesive | 25 to 35 | kg/m² |
| Floating floor + underlay | 8 to 15 | kg/m² |
| Plasterboard partition (H 2.50 m) | 60 to 90 | kg/ml |
When to switch to another solution (available height, overload, acoustics)
If you do not have 40 to 60 mm available, if the projected surcharge exceeds 80 to 100 kg/m², or if acoustics require strict decoupling, switch to a dry screed system or a technical floor build-up. If in doubt about the joist structure, have a structural engineer decide.
Checking the load path on an existing joist floor before pouring
Site data to record: span, section, spacing, timber species, timber condition and perceived deflection
Before a lightweight screed on a timber floor, collect measurable data, not impressions. Record the effective span between supports, the actual section size (width, depth), the spacing, and the presumed species if it can be identified.
- Timber condition. Moisture, decay, cracking, bearing crush, notches and drill holes.
- Floor build-up. Boarding, panels, underlays, partitions sitting on it.
- Deflection. Laser measurement or long straightedge, and any “felt” bounce under foot if possible.
Verification method: permanent loads, imposed loads and the combined floor build-up
Work in area loads. Add the permanent loads (existing and planned layers), then add the regulatory imposed load for the room’s use. Then check the joist stresses and deflection.
| Element | Load type | Typical value (kN/m²) |
|---|---|---|
| Residential imposed load | Variable | 1.5 |
| Underfloor heating, levelling layer, screed | Permanent | To be calculated |
| Floor finish, underlay | Permanent | 0.1 to 0.3 |
When to call a structural engineer: edge cases, older floors, heavy renovation
Call a structural engineer if the section is inconsistent, spans are long, you observe creep, twist, doubtful bearings, or if the project adds partitions, a bathtub, or reinforcements to be created. When in doubt, a calculation note secures professional liability cover and the site file.
Preparing the timber floor: substrate repair and essential decoupling
Repair/reinforcement of the boarding: screw-fixing, panels, local levelling and treatment of soft areas
Before any lightweight screed on a timber floor, start with a substrate that does not move. Re-fix the boarding tightly to the joists with screws, replace worn boards, then stiffen as needed with suitable structural panels. Deal with soft spots at the source. Blocking pieces, bearing repairs or local reinforcement. Spot levelling comes only after that, on a stabilised substrate.
Separation membrane: continuity, upstands, leak-tightness and service penetrations
Lay a film or membrane in full continuity, with joints overlapped and taped. Turn it up at the perimeter to create a tray and secure against laitance leaks through board gaps. For services, provide sleeves, sealed penetrations and neat detailing, with no open punctures left behind; on this point, see also service penetrations.
Compressible perimeter strip: acoustic break, movement allowance and special points (thresholds, posts)
The perimeter strip provides the acoustic break and prevents rigid bridges. Install it before pouring, continuously, including at thresholds and around posts. Special points are treated like edges. If a hard support remains in contact, cracks and sound transmission soon return.
Installing a poured lightweight screed: workmanship rules that prevent cracking and noise
On a lightweight screed over a timber floor, everything depends on decoupling. Continuous film over the boarding, upstands at the perimeter, then compressible strip. This cuts acoustic bridges and allows the screed to move without binding against the walls.
Reinforcement mesh or fibres: choice according to product, thickness and crack risk
Follow the technical assessment and the manufacturer’s data sheet. In practice, you choose between mesh (local load capacity, loaded areas) and fibres (shrinkage, microcracking). Keep regular cover, avoid placing reinforcement on the bottom, and provide a movement joint as soon as any pour interruption is likely.
Minimum thickness and flatness: level references, tolerances and repair areas
| Check | Reference | Value (mm) |
|---|---|---|
| Flatness under straightedge | 2 m straightedge | 5 |
| Local flatness | 20 cm straightedge | 2 |
Set screed rails, check with a laser, and treat repairs as joints. A cold joint without preparation means cracking is almost guaranteed.
Underfloor heating case: minimum cover above pipes and manufacturer compatibility
| Check point | Reference | Minimum (mm) |
|---|---|---|
| Cover above pipes | Top of pipe | 30 |
Confirm compatibility between the lightweight screed and the underfloor heating system (mechanical strength, thermal conductivity, joints). Then carry out a gradual heat-up and record the procedure before flooring.
Drying, heat-up and handover: securing the floor finish installation
Drying time: factors that change everything (thickness, ventilation, humidity, binder) in 2026
With a lightweight screed on a timber floor, give a timeframe based on the product data sheet. Actual thickness, ventilation, relative humidity and binder type affect drying far more than the job programme. Measure; do not assume.
| Parameter | Site effect |
|---|---|
| Thickness | The thicker it is, the longer drying takes |
| Ventilation | Speeds up water removal, without harsh draughts |
| Relative humidity | Above 65% RH, drying slows sharply |
| Binder | Cement: more forgiving. calcium sulphate: more sensitive to moisture |
Gradual heat-up of the underfloor heating: stages, temperatures and checkpoints
Follow a progressive procedure to limit shrinkage and cracking. The goal: stabilise the screed before flooring, then record the temperatures.
| Stage | Water temperature (°C) | Duration (days) |
|---|---|---|
| Start-up | 20 | 3 |
| Ramp-up | +5 per day up to 45 | 5 |
| Hold then ramp down | 45 then -5 per day | 6 |
Site handover report and pre-flooring checks: residual moisture, cracks, flatness and traceability
Before installation, formalise a site handover report. Record residual moisture readings, visual checks and flatness. Attach dated photos, product, batch, thicknesses and ambient conditions.
| Check | Method | Threshold |
|---|---|---|
| Residual moisture | CM carbide test | 2.0% cement. 0.5% sulphate |
| Flatness | 2 m straightedge | 5 mm |
| Cracks | Location and width | Treatment according to manufacturer’s guidance |