Custom secondary glazing is ordered on the smallest of the measurements taken, never on a single one: on old joinery, measure the rebate width and height at three points each and record both diagonals to make the out-of-square visible. The fitting clearance is then set with the workshop that makes the frame, based on that survey, and written on the quote. On funding, promise nothing the obligated supplier has not confirmed: Ofgem's guidance note of 28 September 2026 added secondary glazing to ECO4, but only where an RdSAP assessment would recognise the installation as secondary glazing.
Understanding custom secondary glazing before taking measurements
When secondary glazing makes sense: old joinery and protected areas
Custom secondary glazing is mainly a conservation choice. You are working on old frames of heritage value, on a listed building or in a conservation area where the local planning authority cares about the look of the profiles. Internal secondary glazing does not usually need planning permission unless an Article 4 Direction applies, but a listed building needs listed building consent for any significant works, internal or external. The aim is more comfort without changing the window.
What secondary glazing will not do: limits and funding in 2026
Do not sell it as a window replacement, and quote no Uw until the manufacturer has justified one for the installed assembly. ECO4 is no reason to promise funding either: the two measure types added by Ofgem's guidance note of 28 September 2026 only apply where an RdSAP assessment would recognise the installation as secondary glazing, and the score follows the share of the home's total window area treated, so survey every window rather than only the ones the client points to. Whether a job is funded is for the obligated energy supplier or its managing agent to confirm. The conditions, benefits and limits of secondary glazing in renovation are covered in a dedicated article.
Choosing the right option: fixed, opening, or fitted over an existing sash
| Option | Measurements to take | Key point to watch |
|---|---|---|
| Fixed | Fitting gap, squareness, available depth | Too little clearance on a distorted frame |
| Opening | Opening direction, handle clearance, daylight opening | Added weight, hardware to reinforce |
| Over an existing sash | Admissible thickness, clashes with the ironmongery | Window that no longer closes after fabrication |
Classic trap: taking a single measurement on a twisted frame. Measure at three points per side and write the chosen size on the quote.
Measuring old joinery that is rarely square
Measuring in the right place: rebate, daylight opening, overlaps and sills
First define your reference plane. Record the usable width and height in the frame rebate, then the real daylight opening. Measure the available overlaps, the rebate depth and the condition of the sill. A dated dimensioned sketch, with the opening direction and the hardware, removes ambiguity in fabrication.
| Measurement | Where to take it | Number of readings | Unit |
|---|---|---|---|
| Rebate width | Top, middle, bottom | 3 | mm |
| Rebate height | Hinge side, middle, closing side | 3 | mm |
| Diagonals | Corner to corner | 2 | mm |
| Usable rebate depth | On each side, at the weakest point | 4 | mm |
| Available overlap | On each side | 4 | mm |
Taking several readings: diagonals, out of plumb, bowing and twist
On old joinery, a single measurement is worthless. The difference between the two diagonals shows the out-of-square. Check plumb and flatness with a level or laser, note any bowing or twist, and base the order on the most restrictive value.
Spotting the risk areas: sill upstand, glazing beads, irregular gaps
Spot the hard points: a protruding sill upstand, beads that cannot be removed, crushed seals, an irregular rebate. Record the gaps with a rigid rule, especially in the corners. Take photos and mark where a packer or a special profile will be needed to fit without forcing.
Fitting clearance and tolerances: securing custom fabrication
Having the workshop set the clearances from your survey
The clearance is decided before fabrication, and the workshop sets it for its profile system: it must absorb the out-of-plumb, keep a stable bearing, avoid any rubbing when operated and leave the seal its compression range. Your job is to give it a complete survey and have the chosen clearance written down. The secondary glazing is fitted to the system's certified details and the manufacturer's instructions; for the window itself, BS 8213-4 is the code of practice for survey and installation.
Avoiding the single-measurement trap: minimum size and margin
For secondary glazing added to single glazing, record width and height at three points, plus both diagonals. The fabrication size starts from the minimum measurement, less the clearance set by the workshop. A single measurement on a twisted opening gives a frame that cannot be offered up.
Tolerances to write on the quote
| What appears on the quote | Who sets it |
|---|---|
| Chosen fabrication size (mm) | You, from the minimum measurement |
| Perimeter fabrication clearance (mm) | The workshop, from the survey and its profile |
| Glazing thickness and make-up (mm) | The workshop, according to the available rebate |
| Admissible hardware load (kg) | The hardware manufacturer |
Add an approved dimensioned drawing and a survey sheet signed by the customer to record agreement on the sizes.
Profile, opening direction and admissible glazing thickness
Compatibility with the existing frame: sill, upstand, profile grip and overlap
Feasibility is decided at the survey. Check the sill, the condition of the upstand and the available profile grip, then measure the usable overlap all round. If one side lacks overlap, the workshop must know before choosing its profile.
Glazing thickness and type: what the frame really accepts
Open up the rebate. Measure the usable depth, the bead height and the clearance at the back of the rebate. The admissible thickness also depends on the seals and the risk of pinching when tightened. Check the added weight before approving laminated glass.
Opening direction and accessories: handle, stay, stop, ventilation
Confirm the opening direction against the existing hinges, accessibility and stops. Anticipate clashes between handle and reveal. If you add a stay, a stop or a restrictor, plan the fixing into sound timber or a reinforcement. For ventilation, place the air inlets without weakening the profile.
Added weight, reinforcement and scheduling: getting the installation right first time
Calculating the added weight and comparing it with the hardware
Calculate the glass mass (area × thickness × glass density, 2,500 kg/m³), then compare it with the admissible load of the existing hardware. Check possible pull-out from the substrate and fix the screws into the anchor points that genuinely carry load.
| Glass thickness (mm) | Mass per area (kg/m²) |
|---|---|
| 4 | 10 |
| 6 | 15 |
| 8 | 20 |
| 10 | 25 |
Reinforcing hardware and frame without damaging the existing joinery
If the margin is small, reinforce before fitting: an extra hinge, replaced pins, backing plates or longer screws into sound timber. Avoid holes that split old wood, and check the clearance after tightening.
Scheduling: workshop approval, written lead time and a fallback slot
Send a complete survey (opening, direction, rebates, admissible thickness) and get the workshop's approval before production. Ask for its fabrication lead time in writing and only set the installation date on delivery, with a fallback slot in case an adjustment is needed. Plan these checks into your site handover.
For the first estimate, Argile's opening detection lists every window on the facade from photos of the home, with its dimensions and position. The fabrication sizes of the secondary glazing are then taken in the rebate, with a tape.