Blog/Site handover: the quality control checkpoints
Contractors

May 26, 2026

5 min read

Updated August 10, 2026

Site handover: quality control checklist (2026 edition)

On the day the client walks the site with you, everything comes down to the details. With a simple method and a few checkpoints, you secure quality, avoid costly rework, and walk away with a clear file. For you, it's the moment to turn the end of a job into a real, clean validation, with no grey areas.

Contents

Handover is the act by which the client declares acceptance of the works, with or without snags, and article 1792-6 of the French Civil Code states that it is pronounced in the presence of both parties. It is that date, not the last day on site nor the final invoice, that starts the three statutory warranties: one year of perfect completion under the same article, two years of proper functioning on removable equipment under article 1792-3, ten years of decennial liability under article 1792. A quality control sheet therefore has only one useful purpose, producing on the day a dated, signed and enforceable handover report, with snags worded precisely enough to be cleared without argument.

Preparing the handover: documents, scope and points to watch

Defining the handover scope and the areas to check on site

Before the handover, clarify what is checked and what isn't. List the work packages involved and split the site into zones: heated rooms, loft, basement, plant room. Also identify the interfaces: insulation around joinery, network routing, wall penetrations. That's often where defects hide. Keep an annotated plan or sketch, and settle who will be present on the day. No ambiguity.

Gathering the essential documents: quotes, plans, manuals, technical sheets, test reports

Bring together the signed quotes and amendments, the plans and diagrams (electrical, hydraulic, ventilation), and the manufacturer manuals. For equipment such as a heat pump or mechanical ventilation, prepare the technical sheets, the commissioning record, and the test or settings reports: pressure, flow rates, airtightness, balancing. A clear file avoids arguments when it's time to clear snags. A written trail.

Preparing the quality control equipment: levels, camera, hygrometer, paper or digital checklists

The right equipment saves time. Bring a spirit or laser level, a torch, a camera or smartphone for time-stamped photos, and a hygrometer to check humidity before closing up linings or installing finishes. Add a simple checklist, paper or digital, with a space to note snags, the room, and the date. Clean control.

Quality control by work package: checking execution and compliance on site

Insulation and airtightness: continuity, thermal bridges, vapour barrier and finishes

Before the handover, check the continuity of the insulation. No gaps at the edges, no compression. Track down thermal bridges at floor-wall junctions, load-bearing walls, and window reveals. On the inside, check the vapour barrier. Overlaps, tape, duct and box penetrations must all stay airtight. Finishes must protect the insulation, not puncture it.

Heating, ventilation, controls: commissioning, settings, safety and noise

Commissioning needs to be checked. Control parameters, water curve, emitter balancing, and safety tests. On the ventilation side, validate flow rates and check for no leaks or crushed ducts. If there are complaints, measure noise and correct it. A signed settings log prevents callbacks.

Joinery and finishes: sealing, opening mechanisms, alignment, rework and cleaning

On joinery, sealing makes the difference. Check strips, seals, sills, and water drainage. Opening elements must close without effort, without friction, and stay aligned. Note any rework as a snag, then finish with a thorough clean. This is often what the client remembers most.

Testing, measuring, proving: the checks to carry out on handover day

Functional tests and simple measurements: mechanical ventilation flow rates, temperatures, pressures, humidity differential

On handover day, bring out the instruments. Measure mechanical ventilation flow rates at the vents (values consistent with the sizing), check supply and return temperatures, and check hydraulic network pressures if there's a heat pump or boiler. A reading of the humidity differential before and after start-up also helps objectively assess comfort. Note the date, the instrument used, the measurement point, and the result.

Enhanced visual inspection: dated photos, snag tracking and traceability

Do a full walkthrough, room by room. Take dated photos of sensitive areas (penetrations, ducts, vents, insulation, boxed-in areas). Note snags directly, without going around them, and record them in a signed document. Add traceability of the references installed (labels, serial numbers, manuals) to avoid arguments later.

Checking consistency of expected performance: insulation installed vs. planned, settings vs. client usage

Compare what was installed against what was planned. Insulation thickness and continuity, vapour barrier, treatment of thermal bridges, control settings and setpoints. Confirm actual usage with the client (schedules, heated rooms, ventilation). Two minutes of explanation turns measurements into useful evidence.

Writing the handover report: snags, deadlines and responsibilities

Formulating clear snags: location, defect, photo, rework requirement, deadline

On handover day, aim for precise snags. A vague snag gets argued over, a detailed snag gets fixed. Each snag is better kept in the site file than in a notebook, with Argile tracking it, photos attached, until it is cleared.

  • Exact location (room, wall, reference point).
  • Defect observed, without interpretation.
  • Dated photo, attached to the report.
  • Expected rework requirement (what, how, finish).
  • Realistic, written deadline for clearance.

Managing snag-clearance deadlines and organising the rework on site

Set a written schedule for the rework. Specify who provides access, protection, any shutdowns, and the intervention time slots. After correction, get it validated on site and record the snag clearance in writing.

Securing signatures, the handover date and the transfer of custody of the works

The report must carry a certain date and the signatures of the parties. Note the handover of keys, the appendices, and the snags. Handover triggers the starting point of the legal warranties, even if snags remain to be cleared.

Warranty Duration from handover What it covers Text
Perfect completion 1 year every defect reported, as a snag in the report or by later written notice article 1792-6 of the French Civil Code
Proper functioning 2 years minimum removable equipment elements that can be taken out without damaging the works article 1792-3 of the French Civil Code
Decennial 10 years defects compromising structural soundness or making the works unfit for purpose article 1792 of the French Civil Code

Two practical consequences. A handover pronounced without a dated report leaves the start of all three periods open to argument, which works against you. And on perfect completion, article 1792-6 provides that the time allowed for the remedial works is agreed between client and contractor: no fixed deadline is imposed by the text, so it is for you to write it into the report rather than inherit one.

What a usable quality control sheet actually carries

A generic sheet gets ticked without proving anything. What holds up in a dispute is one line per checkpoint, with the instrument, the reading and the location.

Trade What you check What goes on the sheet
Insulation continuity, no compression, treatment of reveals and junctions thickness and reference of the product installed, time-stamped photos of the detailing
Airtightness laps, tapes, grommets on penetrations, hatches zones treated, photos before closing up linings, test result where one is run
Ventilation flow rates at terminals, no crushed ducts, free air inlets flow measured at each terminal, instrument used, design value targeted
Heating and controls heating curve, balancing, circuit pressure, safety tests control settings, pressure, positions of the balancing devices
Windows and doors sealing, sills, water drainage, operation of opening lights defects found, remedial work expected, deadline for clearance
Substrate moisture level before closing linings and applying finishes value measured, zone, date, threshold from the relevant standard or technical approval

After handover: snag follow-up and useful evidence for checks in 2026

Keeping evidence: report, photos, product sheets, RGE certificates, maintenance manuals

After the handover, file everything in one place. Keep the signed report, dated before-and-after photos, technical sheets and performance data, product references, the company's up-to-date RGE certificate, and the maintenance manuals handed to the client. Add, if possible, the commissioning records (heat pump, mechanical ventilation) and evidence of how critical points were treated.

Ensuring quality follow-up: scheduling snag clearance and the clearance report

Snags are a small draught in the file. Note them, set an intervention date, and confirm clearance with a dated, signed clearance report. Take new photos and keep the client correspondence. This is often what secures an inspection.

For grants, you'll mainly be asked for tidy documents. A detailed invoice (work, quantities, surfaces, performance, address), a signed CEE sworn statement, RGE proof for the right trade area, and, for MaPrimeRénov', the end-of-work documents sent to the client. Prepare a single PDF file, ready to send. To limit rejections, also see our advice on avoiding MaPrimeRénov' application refusals.

Key figures

1 year

warranty of perfect completion, article 1792-6 of the French Civil Code

2 years

warranty of proper functioning on removable equipment, article 1792-3

10 years

decennial liability, article 1792, counted from handover

Frequently asked questions

Set a written deadline in the handover report (often 15 to 30 days depending on the nature of the work) and list each snag with its location, a photo and who is responsible. Have the report signed and schedule a follow-up visit date. Once cleared, produce an amendment to the report or a signed snag-clearance report.

Share this article

Pierre-Louis Guhur

Pierre-Louis is CEO and co-founder of Argile. He holds a PhD in machine learning, written at Inria, and renovated a house with his own hands in 2017 before founding the company. On the blog he writes about what he implements in the software: the 3CL-DPE 2021 method, NF EN 12831 and building physics as a calculation engine has to handle them, assumption by assumption.

Further reading

Site tracking and site reports

With argile

The site report, filled in on site and exported as a PDF

Scheduling, progress, dated photos and snag clearing all feed the site report, exported as a PDF and attached to the customer record, while the end customer follows the same information from their own dedicated space.

ContractorsJuly 2, 2026
Thermal imaging and post-works quality control

After a job, real relief comes from being able to prove everything holds up. With a thermal imaging camera, you can spot thermal bridges, airtightness defects or poorly installed insulation in a few minutes, before the customer discovers them the first winter. That secures your handover, your end-of-job photos and your reputation.

5 min read

ContractorsMay 29, 2026
Insulation PPE: equipment and site safety

On an insulation job, you're juggling dust, cuts, falls and irritant products. With the right PPE and simple habits, you protect your team without slowing the pace, and you keep a clean, professional site. Mask, goggles, gloves, ventilation, clearly defined work zones — this is often where the difference is made.